Engineering , Manufacturing & Supply of 300 Km steel Tower for 230 KV Single Circuit Transmission Line

Syrian Arab Republic

Scope of Work: Supply of about 5619 ton Tower for 230 KV Single Circuit Transmission Line

Employer: Public Establishment for Transmission of Electricity (PETE)

Start & Completion: Started on March 2014 and finished on May 2016

SAMSUNG CAMERA PICTURES

 

 

Engineering , Manufacturing & Supply of 150 Km Steel Tower for 66 KV Double Circuit Transmission Line

Syrian Arab Republic

Scope of Work: Supply of about 4901.8 ton Tower for 66 KV Double Circuit Transmission Line

Employer: Public Establishment for Transmission of Electricity (PETE)

Start & Completion: Started on Feb. 2014 and finished on May 2016

OLYMPUS DIGITAL CAMERA

 

 

Engineering , Manufacturing & Supply of 300 Km Steel Tower for 230 KV Double Circuit Transmission Line

Syrian Arab Republic

Scope of Work:Supply of about 7586.9 ton Tower for 230 KV Double Circuit Transmission Line

Employer: Public Establishment for Transmission of Electricity (PETE)

Start & Completion: Started on March 2014 and finished on May 2016

SAMSUNG CAMERA PICTURES

 

 

 

Engineering , Manufacturing & Supply of 200 Km Steel Tower for 400 KV Single Circuit Transmission Line

Syrian Arab Republic

Scope of Work:Supply of about 8724 ton Tower for 400KV Single Circuit Transmission Line

Employer: Public Establishment for Transmission of Electricity (PETE)

Start & Completion: Started on March 2014 and finished on October 2015